Air Injection Pump Relay: Testing and Inspection

1995 Audi 90 Quattro Sport V6-2.8L (AAH)SECTION Testing and Inspection
REQUIREMENTS
^ Fuel pump relay OK.
^ Secondary Air Injection (AIR) pump relay fuse OK.

NOTE:
The secondary air injection pump relay is located in the fusel relay panel in the right front footwell, relay position -5-.
The fuse for the secondary air injection pump relay is located in fuse position -8-.

CHECKING RELAY POWER SUPPLY
- Switch ignition OFF.

Lower Pillar Cover:





- Remove lower right -A- pillar cover.
- Pull back carpet in right front footwell.





- Pull secondary air injection pump relay out of the relay panel, relay position -5-.
- Connect VAG 1527B voltage tester between terminal 2 of the relay socket and Ground (GND).
^ LED must light up
- Connect VAG 1527B voltage tester between terminal 6 of the relay socket and GND.
^ When starter is operated, LED must light up.

If LED does not light up:
- Repair corresponding open circuit in wiring using wiring diagram.

CHECKING RELAY ACTUATION
- Switch ignition ON.





- Connect VAG 1527B voltage tester between relay socket terminals 2 and 4.
^ LED must dimly light up.
- Initiate output DTM and actuate AIR pump relay -J299-. Refer to On-Board Diagnostics. MMS 311 Engine Management System
^ LED must brighten up for approximately 10 seconds, then dim again.

If LED lights up brighter after actuation (actuation OK):
- Replace secondary air injection pump relay -J299-.

If LED lights up brightly the entire time or does not light at all:
- Check wiring to relay.

CHECKING WIRING TO RELAY
- Connect VAG 1598 test box to wiring harness using adapter cable VAG 1598/11. Refer to VAG 1598 Pin Out Box Connecting. Connecting VAG 1598/31 Test Box
- The adapter harness for ECM is not connected.

If LED lights up continuously bright during relay actuation:
- Check wiring for short circuit to Ground (GND) between relay panel terminal 4 and VAG 1598 test box socket 6.





If LED does not light up during relay actuation:
- Check wiring for continuity between terminal 4 and VAG 1598 test box socket 6.
- If necessary, repair short circuit to GND or open circuit in wiring between relay panel terminal 4 and ECM connector C terminal 6.

If wiring is OK:
- Replace ECM.
RENDER: 1.0x

NO RELATED

Recommended Tools & Savings

Use the Manual With the Right Hardware

Pair factory procedures with proven DIY tools so the instructions are easier to execute.

Affiliate disclosure: We may earn a commission at no extra cost to you.

When to See a Mechanic

Stop DIY work and contact a certified mechanic immediately if any of the following apply:

  • β€’ You smell fuel, burning insulation, or see smoke.
  • β€’ Brakes feel soft, pull hard to one side, or make grinding noises.
  • β€’ The engine overheats, stalls repeatedly, or misfires under load.
  • β€’ You are missing required tools, torque specs, or safe lifting equipment.
  • β€’ You are not confident in the next step or safety outcome.