2013 Toyota Prius CFACTORY OEM SERVICE PROCEDURE

Integration Relay: Inspection: Inspection

  1. INSPECT NO. 1 INTEGRATION RELAY 
    Fig 1: No. 1 Integration Relay Circuit Diagram
    GTY332965Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    TEXT IN ILLUSTRATION

    *1 No. 1 Integration Relay - -
    1. EFI-MAIN Relay:
      1. Measure the resistance according to the value(s) in the table below.
        Fig 2: 2E, 2D, & 2C Terminal Connector
        GTY326781Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
        TEXT IN ILLUSTRATION

        *1 No. 1 Integration Relay

        Standard Resistance

        Tester Connection Condition Specified Condition
        No. 1 Integration relay (2E-1) - No. 1 Integration relay (2C-4) Auxiliary battery voltage is not applied between terminals 2C-3 and 2C-2 10 kΩ or higher
        No. 1 Integration relay (2E-1) - No. 1 Integration relay (2C-4) Auxiliary battery voltage is applied between terminals 2C-3 and 2C-2 Below 1 Ω

        If the resistance is not as specified, replace the No. 1 integration relay.

    2. HORN Relay:
      1. Measure the resistance according to the value(s) in the table below.
        Fig 3: 2E, 2D, & 2C Terminal Connector
        GTY326781Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
        TEXT IN ILLUSTRATION

        *1 No. 1 Integration Relay

        Standard Resistance

        Tester Connection Condition Specified Condition
        No. 1 Integration relay (2E-1) - No. 1 Integration relay (2C-8) Auxiliary battery voltage is not applied between terminals 2C-6 and 2C-7 10 kΩ or higher
        No. 1 Integration relay (2E-1) - No. 1 Integration relay (2C-8) Auxiliary battery voltage is applied between terminals 2C-6 and 2C-7 Below 1 Ω

        If the resistance is not as specified, replace the No. 1 integration relay.

    3. IG2 Relay:
      1. Measure the resistance according to the value(s) in the table below.
        Fig 4: 2E, 2D, & 2C Terminal Connector
        GTY326781Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
        TEXT IN ILLUSTRATION

        *1 No. 1 Integration Relay

        Standard Resistance

        Tester Connection Condition Specified Condition
        No. 1 Integration relay (2E-1) - No. 1 Integration relay (2D-4) Auxiliary battery voltage is not applied between terminals 2D-2 and 2D-3 10 kΩ or higher
        No. 1 Integration relay (2E-1) - No. 1 Integration relay (2D-4) Auxiliary battery voltage is applied between terminals 2D-2 and 2D-3 Below 1 Ω

        If the resistance is not as specified, replace the No. 1 integration relay.

    4. C/OPN Relay:
      1. Measure the resistance according to the value(s) in the table below.
        Fig 5: 2E, 2D, & 2C Termional Connector
        GTY326781Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
        TEXT IN ILLUSTRATION

        *1 No. 1 Integration Relay

        Standard Resistance

        Tester Connection Condition Specified Condition
        No. 1 Integration relay (2D-5) - No. 1 Integration relay (2D-8) Auxiliary battery voltage is not applied between terminals 2D-6 and 2D-7 10 kΩ or higher
        No. 1 Integration relay (2D-5) - No. 1 Integration relay (2D-8) Auxiliary battery voltage is applied between terminals 2D-6 and 2D-7 Below 1 Ω

        If the resistance is not as specified, replace the No. 1 integration relay.

Factory Service Tools

Use the Manual With the Right Hardware

Pair factory procedures with proven DIY tools so the instructions are easier to execute.

Disclosure: Verified tool recommendations may earn an affiliate commission at no cost to you.

When to See a Mechanic

Stop DIY work and contact a certified mechanic immediately if any of the following apply:

  • • You smell fuel, burning insulation, or see smoke.
  • • Brakes feel soft, pull hard to one side, or make grinding noises.
  • • The engine overheats, stalls repeatedly, or misfires under load.
  • • You are missing required tools, torque specs, or safe lifting equipment.
  • • You are not confident in the next step or safety outcome.