2021 Subaru WRX BaseFACTORY OEM SERVICE PROCEDURE

Engine Starting System & Charging System (2.0L): Generator: Inspection: Rotor

  1. Slip ring surface

    Inspect the slip rings for contamination or any roughness on the sliding surface. Repair the slip ring surface using a lathe or sand paper.

  2. Slip ring outer diameter

    Measure the slip ring outer diameter. Replace the rotor if the slip ring is worn.

    Slip ring outer diameter: 

    Standard 

    22.7 mm (0.894 in)

    Limit 

    22.1 mm (0.870 in)

  3. Continuity test

    Using a circuit tester, check the resistance between slip rings. If the resistance is not within the standard, replace the rotor.

    Standard: 

    Approx. 2.0 - 2.4 Ω

    G07665195Courtesy of SUBARU OF AMERICA, INC.
  4. Insulation test

    Check the continuity between slip ring and rotor core or shaft. If there is continuity, replace the rotor because the rotor coil is grounded.

    G07665196Courtesy of SUBARU OF AMERICA, INC.
  5. Bearing

    Check the bearings. If there is any noise, or the rotor does not rotate smoothly, replace the bearings.

Factory Service Tools

Use the Manual With the Right Hardware

Pair factory procedures with proven DIY tools so the instructions are easier to execute.

Disclosure: Verified tool recommendations may earn an affiliate commission at no cost to you.

When to See a Mechanic

Stop DIY work and contact a certified mechanic immediately if any of the following apply:

  • • You smell fuel, burning insulation, or see smoke.
  • • Brakes feel soft, pull hard to one side, or make grinding noises.
  • • The engine overheats, stalls repeatedly, or misfires under load.
  • • You are missing required tools, torque specs, or safe lifting equipment.
  • • You are not confident in the next step or safety outcome.