OIL CONTROL VALVE (OCV) INSPECTION
Coil Resistance Inspection

1. Measure the coil resistance between terminals A and B using the tester.
- If not within the specification, replace the oil control valve (OCV).
OCV coil resistance 6.9-7.9 ohms [20° C {68° F}]
Spool Valve Operation Inspection

1. Verify that the spool valve in the oil control valve (OCV) is in the maximum valve timing retard position as shown in the figure.
- If it cannot be verified as shown, replace the oil control valve (OCV).
2. Apply battery positive voltage between the oil control valve (OCV) terminals A and B, and verify that the spool valve operates and moves to the maximum valve timing advance position.
- If it cannot be verified as shown in the figure, replace the oil control valve (OCV).
Note: When applying battery positive voltage between the oil control valve (OCV) terminals, the connection of the positive and negative battery cable can be with either of the oil control valve (OCV) terminals.

3. Stop applying battery positive voltage and verify that the spool valve returns to the maximum valve timing retard position.
- If it cannot be verified as shown in the figure, replace the oil control valve (OCV).
Coil Resistance Inspection
1. Measure the coil resistance between terminals A and B using the tester.
- If not within the specification, replace the oil control valve (OCV).
OCV coil resistance 6.9-7.9 ohms [20° C {68° F}]
Spool Valve Operation Inspection
1. Verify that the spool valve in the oil control valve (OCV) is in the maximum valve timing retard position as shown in the figure.
- If it cannot be verified as shown, replace the oil control valve (OCV).
2. Apply battery positive voltage between the oil control valve (OCV) terminals A and B, and verify that the spool valve operates and moves to the maximum valve timing advance position.
- If it cannot be verified as shown in the figure, replace the oil control valve (OCV).
Note: When applying battery positive voltage between the oil control valve (OCV) terminals, the connection of the positive and negative battery cable can be with either of the oil control valve (OCV) terminals.
3. Stop applying battery positive voltage and verify that the spool valve returns to the maximum valve timing retard position.
- If it cannot be verified as shown in the figure, replace the oil control valve (OCV).
Factory Service Tools
Use the Manual With the Right Hardware
Pair factory procedures with proven DIY tools so the instructions are easier to execute.
Disclosure: Verified tool recommendations may earn an affiliate commission at no cost to you.
When to See a Mechanic
Stop DIY work and contact a certified mechanic immediately if any of the following apply:
- β’ You smell fuel, burning insulation, or see smoke.
- β’ Brakes feel soft, pull hard to one side, or make grinding noises.
- β’ The engine overheats, stalls repeatedly, or misfires under load.
- β’ You are missing required tools, torque specs, or safe lifting equipment.
- β’ You are not confident in the next step or safety outcome.