2009 Land Rover LR2 (LF) L6-3.2LFACTORY OEM SERVICE PROCEDURE

Starting System: Service and Repair

Ignition Switch

Service Repair No - 86.65.02


Removal

1. Make the SRS system safe.
2. Remove the driver lower air bag module.

3. NOTE: RHD illustration shown, LHD is similar.

Remove the keyless start control module trim cover.

Factory service manual diagram




4. Remove the steering column lower cowl.

Factory service manual diagram




5. Adjust the steering column to its lowest position.

6.

Factory service manual diagram




7. NOTE: Take extra care when releasing the clips.

Remove the instrument cluster surround.

Factory service manual diagram




8. Remove the ignition switch.

Factory service manual diagram




Installation

1. To install, reverse the removal procedure.
Factory Service Tools

Use the Manual With the Right Hardware

Pair factory procedures with proven DIY tools so the instructions are easier to execute.

Disclosure: Verified tool recommendations may earn an affiliate commission at no cost to you.

When to See a Mechanic

Stop DIY work and contact a certified mechanic immediately if any of the following apply:

  • β€’ You smell fuel, burning insulation, or see smoke.
  • β€’ Brakes feel soft, pull hard to one side, or make grinding noises.
  • β€’ The engine overheats, stalls repeatedly, or misfires under load.
  • β€’ You are missing required tools, torque specs, or safe lifting equipment.
  • β€’ You are not confident in the next step or safety outcome.