2002 Isuzu Rodeo LS, 2.2 DFACTORY OEM SERVICE PROCEDURE

Installation (4X2 Model)

  1. Install power steering unit to crossmember.

    Tighten fixing bolt to specified torque.

    Torque:  116 N.m (85 lb ft)

  2. Connect the feed line and return line.

    Torque:  25 N.m (18lb ft)

  3. Install tie-rod end assembly to knuckle.

    Torque:  118 N.m (87 lb ft)

    1. Align the setting marks made at removal. Install the universal joint assembly to the transfer gear assembly.

      Temporary tighten the universal joint bolt.

    2. Install the universal joint assembly to the power steering unit assembly.

      Temporary tighten the universal joint bolt.

    3. Install the transfer gear assembly with the shim to frame.

      Torque:  54 N.m (40 lb ft)

    4. Tighten the universal joint bolt to the specified torque.

      Torque:  31 N.m (23 lb ft)

  4. Install the stone guard.
  5. Bleed the system. Refer to BLEEDING THE POWER STEERING SYSTEM  .
Factory Service Tools

Use the Manual With the Right Hardware

Pair factory procedures with proven DIY tools so the instructions are easier to execute.

Disclosure: Verified tool recommendations may earn an affiliate commission at no cost to you.

When to See a Mechanic

Stop DIY work and contact a certified mechanic immediately if any of the following apply:

  • • You smell fuel, burning insulation, or see smoke.
  • • Brakes feel soft, pull hard to one side, or make grinding noises.
  • • The engine overheats, stalls repeatedly, or misfires under load.
  • • You are missing required tools, torque specs, or safe lifting equipment.
  • • You are not confident in the next step or safety outcome.