1989 Geo Tracker Base, AutomaticFACTORY OEM SERVICE PROCEDURE

System Performance Test 6 (Fuel-Cut System Operational Check Spectrum)

  1. Warm engine until choke is fully open and A/C off. Connect tachometer. Connect voltmeter between ground and terminal "B" of fuel-cut relay See Fig 1 .
  2. Open throttle slightly and keep engine at 3500 RPM. Note voltage. If voltage is less than 6 volts, go to step 3). If voltage is greater than 6 volts, check for open between terminal "B" and ECM terminal No. 14. If circuit is not open, adjust idle switch. If adjustment is okay, ECM or connection is bad.
  3. Return throttle to idle while checking voltage. If voltage changes, go to step 4). If voltage does not change, check adjustment of idle switch and A/C fast idle diaphragm.
  4. If voltage rises greater than 6 volts, then falls again to low level when engine drops below 2000-2500 RPM, fuel-cut circuit and idle switch adjustment are okay. If A/C equipped, repeat test with A/C on.
Fig 1: Fuel Cut Relay Wiring Diagram
G121716Courtesy of GENERAL MOTORS CORP.
Factory Service Tools

Use the Manual With the Right Hardware

Pair factory procedures with proven DIY tools so the instructions are easier to execute.

Disclosure: Verified tool recommendations may earn an affiliate commission at no cost to you.

When to See a Mechanic

Stop DIY work and contact a certified mechanic immediately if any of the following apply:

  • β€’ You smell fuel, burning insulation, or see smoke.
  • β€’ Brakes feel soft, pull hard to one side, or make grinding noises.
  • β€’ The engine overheats, stalls repeatedly, or misfires under load.
  • β€’ You are missing required tools, torque specs, or safe lifting equipment.
  • β€’ You are not confident in the next step or safety outcome.